Construction began in May 2025, with completion scheduled for 2027

SAN DIEGO COUNTY — A massive infrastructure project is currently reshaping one of North County San Diego's most critical transportation arteries, as the California Department of Transportation (Caltrans) undertakes a comprehensive $126 million rehabilitation of State Route 78.

The SR-78 Asset Management Project, which began construction in May 2025, encompasses a 17.7-mile stretch from Interstate 5 in Oceanside to Broadway and Lincoln Parkway in Escondido. The ambitious undertaking represents one of the largest highway improvement efforts in the region, focusing on preserving existing infrastructure while modernizing the corridor to meet current and future transportation demands.

Comprehensive Infrastructure Overhaul

The project goes far beyond simple resurfacing, incorporating what Caltrans describes as "asset management principles" to improve multiple aspects of the highway system. Workers are repaving 80 lane miles and rebuilding 91 pedestrian crossings with ADA-compliant curb ramps, while simultaneously upgrading 48 guardrail systems to reduce collision severity.

"The project will rehabilitate pavement along the main roadway, shoulders, and freeway ramps to extend the life of the existing highway," according to Caltrans documentation. The work includes cold planing and overlaying the traveled way, shoulders, and entrance/exit ramps.

Among the most significant improvements is the construction of an eastbound lane between Las Posas Road and San Marcos Boulevard, along with the widening of the Mar Vista Drive bridge. The project also includes extensive modernization of Traffic Management Systems (TMS), featuring new CCTV locations, ramp metering systems, loop detectors, and fiber optic installations.

Safety and Technology Enhancements

Safety improvements form a cornerstone of the project, with officials noting that "addressing pavement defects, reducing the risk of crashes caused by poor road conditions" is a primary goal. The comprehensive approach includes bridge rail upgrades, enhanced drainage systems for stormwater management, and new sign panels with improved lighting.

The technological upgrades are particularly extensive, featuring Intelligent Transportation Systems (ITS) improvements that include traffic monitoring equipment, vehicle detection systems, cameras, and census counters. Additionally, Weigh-In-Motion systems are being upgraded to improve freight operations throughout the corridor.

Traffic Impact and Construction Schedule

Motorists can expect significant but carefully managed disruptions during the two-year construction period. Daytime work is conducted from 6:30 a.m. to 3:30 p.m., while intermittent ramp and lane closures occur in the evening from 9:00 p.m. to 5:00 a.m. The most substantial impacts will be full roadway closures in both eastbound and westbound directions east of Rancho Santa Fe Road during evening hours.

The project timeline demonstrates extensive planning, with environmental studies completed between 2020-2022 and design work finished in 2024. Construction will continue through 2027, representing a significant investment in the region's transportation infrastructure.

Funding and Regional Context

The $126 million project is funded through the State Highway Operation Protection Program, with $111.5 million in federal funds (including $9.2 million from the Infrastructure Investment and Jobs Act) and $14.5 million in state funds.

The SR-78 Asset Management Project is part of a broader initiative to improve North County transportation infrastructure. State Route 78 serves as "the primary east-west travel corridor between the cities of Escondido and Oceanside," crossing through Carlsbad, Vista, and San Marcos while providing crucial connections to Interstates 5 and 15.

Related Regional Projects

The asset management project operates alongside several other major transportation initiatives in the SR-78 corridor. The I-15/SR-78 Managed Lanes Direct Connectors project, currently in environmental review, has an estimated cost of $490 million and is anticipated for construction in 2030, pending funding. The Draft Environmental Impact Report for this project was released for public review on May 19, 2025, with comments accepted through July 7.

Additionally, Caltrans is evaluating concepts to improve the I-5/SR-78 interchange, with $8 million available for preliminary design and environmental studies and an Environmental Impact Report expected to be completed by 2029.

Historical Context

The current work comes after the corridor experienced significant challenges in recent years. In March 2023, a massive sinkhole appeared during atmospheric river storms, leading to a nearly two-month closure of sections of SR-78 near MiraCosta College, with emergency repairs costing approximately $20 million.

Long-Term Benefits

Officials emphasize that the current project represents a cost-effective approach to infrastructure maintenance. "Preventative rehabilitation is significantly more economical than full reconstruction" and helps reduce the environmental impact compared to building new highways.

The comprehensive nature of the improvements is designed to provide long-term benefits, extending pavement life through rehabilitation and reducing the need for major future repairs. Enhanced mobility through upgraded traffic management systems and infrastructure improvements are expected to support smoother, more reliable travel throughout the corridor.

For commuters and residents in North County, the SR-78 Asset Management Project represents a significant investment in the region's transportation future, promising improved safety, reduced congestion, and modernized infrastructure to serve the growing population and economic activity in the area.

For project updates and traffic information, motorists can contact Caltrans at ct.public.information.D11@dot.ca.gov or call (619) 688-6670.


Sources

  1. North County Daily Star. "SR-78 Asset Management Project -Project Overview." northcountydailystar.com. Accessed August 13, 2025.
  2. California Department of Transportation. "SR-78 Asset Management Project." Caltrans District 11. https://dot.ca.gov/caltrans-near-me/district-11/current-projects/sr78-projects/sr78-assetmanagement
  3. California Department of Transportation. "SR-78 Projects." Caltrans District 11. https://dot.ca.gov/caltrans-near-me/district-11/current-projects/sr78-projects
  4. California Department of Transportation. "Draft EIR for I-15/SR-78 Interchange Released for Public Review and Comment." May 19, 2025. https://dot.ca.gov/caltrans-near-me/district-11/news/20250519-drafteir-i15sr78project
  5. California Department of Transportation. "I-15/SR-78 Managed Lanes Direct Connectors and Woodland Parkway Interchange Project." https://dot.ca.gov/caltrans-near-me/district-11/current-projects/sr78-projects/i15sr78-expresslanes
  6. California Department of Transportation. "I-5/SR-78 Interchange Project." https://dot.ca.gov/caltrans-near-me/district-11/current-projects/sr78-projects/i5sr78-interchange
  7. San Diego Association of Governments (SANDAG). "SR 78 Corridor Improvements." https://www.sandag.org/projects-and-programs/roads-and-highways/road-and-highway-projects/sr-78-corridor-improvements
  8. San Diego Association of Governments (SANDAG). "I-5/SR 78 Interchange Improvements." https://www.sandag.org/projects-and-programs/roads-and-highways/road-and-highway-projects/sr-78-corridor-improvements/i-5-sr-78-interchange-improvements
  9. San Diego Association of Governments (SANDAG). "I-15/SR 78 Managed Lanes Direct Connectors." https://www.sandag.org/projects-and-programs/roads-and-highways/road-and-highway-projects/sr-78-corridor-improvements/i-15-sr-78-managed-lanes-direct-connectors
  10. KPBS Public Media. "Stretch of eastbound SR-78 in Oceanside closed for repairs." April 6, 2023. https://www.kpbs.org/news/local/2023/04/05/stretch-of-eastbound-sr-78-in-oceanside-closed-for-repairs
  11. NBC San Diego. "After Nearly 2 Months of Traffic Detours, SR-78 in North County San Diego Finally Reopens." May 9, 2023. https://www.nbcsandiego.com/news/local/after-months-of-traffic-detours-sr-78-in-north-county-san-diego-to-finally-reopen/3223682/
  12. SR-78 Asset Management Project -Project Overview | North County Daily Star

Comments

Popular posts from this blog

In 5 years since investigation, little progress in stopping deaths in San Diego County jails – San Diego Union-Tribune

Battery Energy Storage Systems Project | Safety Standards for BESS in San Diego County

Miramar Road property zoned for housing is sold